23/07/2025 - Alex Randall and Sam Hill - 2hrs
SH moved all the spoil stacked at the bottom of South Pot to the 166' tunnel. Reported zero winch cut outs, so the smaller generator is definitely the way forward.
AR drilled the next round to extend the dig. Alternating between drills to avoid repeating the drill breakdowns from earlier in the year the following was drilled. Six 16mm holes in an arch to keep the current dimensions of the crawl as we move forward, and four 12mm holes further ahead in the tight section, hopefully enough to allow a very thin person to squeeze through...
Had some minor technical difficulties get the loud noise to happen, but very loud when it did go. New batteries needed in the noise initiator needed it seems.