30/09/2025 - Evening

 30/09/2025 - Evening AR, SH - 2hrs

Took 6 shortish scaff tubes and some tools down, and collected the second half of the Homeclose ladder from the Echo Tunnel.

Bolted the ladder back together, loosely as we'd forgotten proper spanners, and cut a couple tubes down to length. Offered the ladder into position, and worked out how many base jacks and ladder clips we'll need.

Then AR used the drill to chisel off a bulge that will be in the way while SH removed and packaged some old electrical cables and lights that don't work. Then the remainder of the session was used moving this rubbish and the last bags of spoil from the bottom of Echo to the top.

Will need a third person next week to help hold the ladder while the scaff tubes are jacked into position.